MAITRE D’OUVRAGE: CH DE CLUNY
ENTREPRISE (EN CAS DE SOUS TRAITANCE): LIMOGE REVILLON
NOM DU CHANTIER: RECONSTRUCTION DU CENTRE HOSPITALIER DE CLUNY PHASE 3 RESTRUCTURATION BATIMENT SOUS LES VIGNES LOT 04 GROS ŒUVRE – RENFORCEMENTS DE PLANCHER
DEP: 71
LIEU: CLUNY
MARCHE DE BASE HT: 82 000€
AVENANT HT: 17 517,60€
MONTANT GLOBAL HT: 99 517,60€
DESCRIPTIF: RENFORT DE PLANCHER
ANNEE DE REALISATION: 2018
DEBUT PREVU: 15/10/2018
DUREE: 2 SEMAINES
AXIS
12 mai 2016